[E4] Tohoku Expressway between Koriyama Minami IC and Koriyama JCT
Implemented all-day face-to-face traffic regulation due to bridge renewal work

  • Corporate Top
  • Press Room
  • Press Release Tohoku office
  • [E4] Tohoku Expressway Koriyama Minami IC-Koriyama JCT Bridge Ryo Implemented all-day face-to-face traffic regulation due to renewal work

The latest regulatory information isDraTraPlease see.

PDF version [PDF: 784KB]

Expressway renewal project logo image image 1

April 8, 4th year of Reiwa
East Nippon Expressway Co., Ltd.
Tohoku Regional Head Office Koriyama management office

NEXCO EAST Koriyama Management Office (Koriyama City, Fukushima Prefecture) is located between the E4 Tohoku Expressway Koriyama Minami Interchange (IC) and Koriyama Junction (JCT). ) In order to replace the old reinforced concrete slab with a new slab at the bridge, the section of 2 lanes on each of the upper and lower lines will be reduced to 1 lane each, and all-day face-to-face traffic restrictions will be restricted to one side on Tuesday, May 24. ).
Since the construction will reduce the number of lanes that can be driven from two lanes to one lane, traffic congestion is predicted on holidays near the construction site between Koriyama Minami IC and Koriyama JCT on the Tohoku Expressway.
We apologize for any inconvenience caused to our customers, but when traveling in the section concerned, please make efforts for safer driving and go out with plenty of time. In addition, if you are planning to use the construction section on a holiday, please consider detouring to Joban Expressway or general road, changing the outing time, or using public transportation.
Renewal work is necessary to use the Expressway safely and securely. We will do our best to minimize the inconvenience to our customers, so we ask for your understanding and cooperation.

◆Construction image photograph

[Old floor slab removal status] photo
[Removal of old slabs]
[New floor slab installation status] photo
[New slab installation status]
[Surface traffic regulation status] photo
[Restrictions on face-to-face traffic]

1. 1. Traffic regulation section

Tohoku Expressway Koriyama Minami IC-Koriyama JCT (upper and lower lines)

Image of position map
Image image of construction section

2. Traffic regulation period and traffic congestion forecast

  1. Traffic regulation period
    May 19th (Thursday) -June 28th (Tuesday) (41 days)
  2. Image of traffic regulation period (May)
    Image of traffic regulation period (June)

    【Usage Guide】
    All-day lane regulation implementation date (10 days)
    All-day face-to-face traffic regulation implementation date (31 days)

    • Saturday and Sunday are also regulated throughout the day.
    • The traffic regulation period may change depending on the progress of construction.
  3. Congestion forecast
    During the construction period, we anticipate traffic congestion of up to about 5km on holidays. The time of traffic congestion is predicted to be around 15:00 to 21:00 on the In-bound line, so please consider detouring to Joban Expressway or general roads, changing the outing time, or using public transportation.

3. Traffic restrictions

For the floor slab replacement work, the section of each of the two lanes on the upper and lower lanes will be reduced to one lane each, and will be consolidated on one side to implement two-way traffic restrictions throughout the day. During the first and last few days of the construction period, lane restrictions will be applied to both the upper and lower lanes as a preparatory work for switching lanes.

◆Image of lane regulation and two-way traffic regulation

Image of lane regulation
Image of face-to-face traffic regulation

Four. Construction content

Approximately 48 years have passed since the opening of the Mabangawa Bridge, which is located between the Koriyama Minami IC and Koriyama IC on the Tohoku Expressway As a result of such factors as deterioration of the concrete deck and rust on the reinforcing bars, it is necessary to carry out drastic anti-aging work.
By replacing the deteriorated existing concrete deck with a new deck, it will be reborn as an Expressway

◆ Construction overview

Image image of construction outline

Five. Request when using

  1. The construction section will be restricted to face-to-face traffic throughout the day for approximately 3.9km. The current two lanes on each side will be reduced to one lane, and it is predicted that traffic congestion will exceed about 5 km at the beginning of the construction site, so detours to Joban Expressway and general roads, change of outing time or public transportation Please consider using it.
  2. Since the driving lane and shoulders are narrow in the two-way traffic restricted section, please observe the regulated speed when driving, secure the inter-vehicle distance, and be careful about rear-end collisions. In addition, the lanes will change significantly before and after the two-way traffic regulation section, so please follow the local information signs.
  3. Vehicles for construction work may enter and leave the area around the construction site, so please be careful when traveling ahead.
  4. During the construction period, we will provide traffic congestion information using LED information boards, provide construction regulation information using road information boards and road signs, and call attention to driving safely. Please check this information before driving and drive safely.

◆ Photograph of information provided around the construction site

[LED information board] photo
[LED information board]
[Road information board] photo
[Road information board]
[Construction control material] photo
[Construction regulation materials]

6. Efforts to minimize inconvenience to customers due to construction work

[Adopting precast products for the purpose of shortening construction period and improving quality]
By adopting a precast PC floor slab, the construction period has been shortened compared to usual, and the regulation period has been shortened to the maximum.
*Precast is a product manufactured in advance at a factory, etc.

[Advance notice of construction regulations and traffic jam information by TV commercials, construction website, etc.]
We will inform you in advance of the regulation contents by TV commercials, construction websites, signboards, etc., mainly in the Tohoku region.

[Notice image] * This is a public relations material for the renewal work carried out in the 3rd year of Reiwa.

◆ TV commercial

Image image of TV commercial

◆ HP dedicated to construction

Image image of HP for construction only

◆ Stand sign

Photo of the signboard

7. How to obtain road traffic information

  • DraPla", a site full of useful information on Expressway nationwide
    【address】
    PC version (https://www.driveplaza.com/)
    Mobile version (http://m.driveplaza.com/)
    Smartphone version (http://www.driveplaza.com/smp/)
  • Expressway traffic information service "Drive Traffic (DraTra)"
    (Https://www.drivetraffic.jp/construction-regulation)
    It provides real-time road traffic information.
    【address】
    PC version (https://www.drivetraffic.jp/)
    Mobile version (http://m.drivetraffic.jp/)
    Smartphone version (http://www.drivetraffic.jp/smp/)
  • NEXCO東日本お客さまセンター
    24時間365日オペレーターが応対いたします。
    【電話番号】
    0570-024-024(ナビダイヤル) または 03-5308-2424
  • 日本道路交通情報センター(JARTIC)
    【アドレス】 https://www.jartic.or.jp/
    【電話番号】
    全国共通ダイヤル 050-3369-6666 (携帯短縮ダイヤル #8011
    ※全国どこからでも最寄りの情報センターに接続します。
    福島情報 050-3369-6607
    東北地方高速情報 050-3369-6761
  • Highway radio
    Highway radio (AM1620kHz)
    The section that is broadcasting is indicated by the sign on Expressway.
  • Highway Information Terminal
    Wide-area road traffic information is notified on the monitor screen installed in SA / PA.
  • Official Twitter account
    "NEXCO EAST (Tohoku)" (@e_nexco_tohoku) Provides information on Expressway in the Tohoku region.
Expressway renewal project logo image image 2

Expressway renewal project
Now, safety and security are passed on to the next generation.
NEXCO EAST will work on a large-scale renewal and repair business of Expressway in order to provide you with safety and security.
Or search for "high-speed renewal".

The NEXCO EAST Group has positioned the period from 2021 to 2025 as "a period that contributes to the achievement of the SDGs and transforms into a new future society," and is making various efforts.
We believe that this "renewal work" initiative will contribute to the SDGs goals No. 8, 9, and 11 as business activities that lead to the development of safe, secure, and reliable infrastructure.

Image image of SUSTAINABLE DEVELOPMENT GOALS logo and No. 8 logo for economic growth that is rewarding to work, No. 9 logo for creating a foundation for industry and technological innovation, and No. 11 logo for community development that allows people to continue living.
Image link (external link) to download page of Adobe Acrobat Reader

To view the PDF file, you need the Adobe Systems plug-in software "Acrobat Reader (Japanese version)". If you do not have​​​ Download from here (free)Please use it.