[E4] Between Tohoku Expressway Ashiro IC and Kazuno Hachimantai IC
Due to bridge and tunnel renewal work
Implementation of all-day face-to-face traffic regulation

  • Corporate Top
  • Press Room
  • Press Release Tohoku office
  • [E4] Implementation of all-day face-to-face traffic restrictions due to bridge renewal work between Tohoku Expressway

The latest regulatory information isDraTraPlease see.

PDF version [PDF: 572KB]

Expressway renewal project logo image image 1

April 5, 3rd year of Reiwa
East Nippon Expressway Co., Ltd.
Tohoku Regional Head Office Towada management office

NEXCO EAST Towada Management Office (Kazuno City, Akita Prefecture) has introduced a new reinforced concrete slab between the E4 Tohoku Expressway Ashiro Interchange (IC) and Kazuno Hachimantai IC. Due to the replacement work and tunnel repair work, the section of 2 lanes on each of the upper and lower lanes will be reduced to 1 lane each, and the all-day two-way traffic regulation will be enforced from May 25 (Tuesday).
We apologize for any inconvenience caused to our customers, but if you drive in the section, please try to drive more safely and leave with plenty of time.
Renewal work is necessary to use the Expressway We will do our best to minimize the inconvenience to our customers, so we ask for your understanding and cooperation.

◆Construction image photograph

[Surface traffic regulation status] photo
[Restrictions on face-to-face traffic]
[Floor slab removal status] photo
[Floor slab removal status]
[Tunnel repair status] photo
[Tunnel repair status]

1. Traffic regulation section

Tohoku Expressway Ashiro IC and Kazuno Hachimantai IC

Tohoku Expressway Ashiro IC and Kazuno Hachimantai IC

2. Traffic regulation period

 令和3年5月6日(木)~8月15日(日)(102日間)
 (※湯瀬(ゆぜ)パーキングエリア(PA)(上り線)は令和3年5月25日(火)~7月29日(木)まで終日閉鎖となります。)

Image of traffic regulation period (May)
Image of traffic restriction period (June)
Image of traffic regulation period (July)
Image of traffic regulation period (August)

【Usage Guide】

 終日車線規制 実施日(36日間)
 終日対面通行規制 実施日(66日間)

  • Saturday, Sunday and public holidays are also regulated throughout the day.
  • The regulation period may change depending on the progress of construction work.

3. Traffic restrictions

For the floor slab replacement work, the section of each of the two lanes on the upper and lower lanes will be reduced to one lane each, and will be consolidated on one side to implement two-way traffic restrictions throughout the day. Due to two-way traffic restrictions, the In-bound line of Yuze PA will be closed. During the first and last few days of the construction period, all-day lane regulation will be applied to the upper and lower lanes as a preparatory work for switching lanes.

◆ Face-to-face traffic regulation image

Image before and after face-to-face traffic regulation
Image image at the time of face-to-face traffic regulation

Four. Construction content

Tohoku Expressway Yashiro IC and Kazuno Hachimantai IC, and the traffic volume of large vehicles has increased and the total weight per vehicle has increased. Since the concrete has deteriorated and the reinforcing bars have rusted due to the salt content of the antifreeze agent in snow and ice work, it is necessary to carry out drastic anti-aging work. At Tengu Bridge, work will be carried out to replace the deteriorated existing concrete slab with a new slab, and at the Tayama Tunnel and 5 other tunnels, repair work will be carried out to prevent concrete pieces from falling.
In addition, we also carry out pavement repair work, road maintenance work, and detailed road inspections.

◆ Construction overview

Image image of construction overview 1
Image image of construction outline 2

Five. Request to customers

  1. The construction section will be restricted to face-to-face traffic throughout the day for approximately 15km. Although it is not predicted that traffic jams will occur, please try to drive safely when using the section, and please leave plenty of time when using it.
  2. During the construction period, the driving lane and shoulders will be narrowed, so please observe the regulated speed when passing, secure the distance between vehicles, and be careful about rear-end collisions. In addition, the lanes will change significantly before and after the two-way traffic regulation section, so please follow the local information signs.
  3. Vehicles for construction work may enter and leave the area around the construction site, so please be careful when traveling ahead.
  4. During the construction period, we will provide construction regulation information using road information boards, simple LED information boards, and road signs, and call for caution so that people can pass safely. Please check this information before passing, and pass safely.
  5. During the construction period, you will not be able to use In-bound Those who use the highway bus will not be able to get on and off at In-bound We apologize for the inconvenience, as alternative transportation of highway buses will be carried out between the highway bus stop "Kazuno Antora Mae" in front of Road Station Kazuno Antora and JR "Yuse Onsen Station". However, please use that. Please see the Kazuno Kiritanpo FM homepage for details on alternative transportation methods and fees.

◆ Photograph of information provided around the construction site

[Road information board] photo
[Road information board]
[Simple LED information board] photo
[Simple LED information board]
Image of [road sign]
[Road sign]

6. Efforts to minimize inconvenience to customers due to regulations

[Adoption of precast products for the purpose of shortening the construction period and improving quality]
By adopting the floor slab of precast products, the regulation period is shorter than usual.
* Precast is to manufacture products in advance at factories, etc.

[Advance notice of regulation contents by TV commercials, radio commercials, newspaper advertisements, etc.]
We will inform you in advance of the regulation contents by TV commercials, radio commercials, newspaper advertisements, etc., mainly in the Tohoku region.

◆ TV commercial image

Image image of TV commercial image

◆ Leaflet image

Leaflet image image image

◆ Poster image

Image of poster image

7. 7. How to obtain customer traffic information

  • DraPla)", a site full of useful information on Expressway
    【address】
    PC version (https://www.driveplaza.com/)
    Mobile version (http://m.driveplaza.com/)
    Smartphone version (http://www.driveplaza.com/smp/)
  • Expressway traffic information site "Drive Traffic (DraTra)"
    It provides real-time road traffic information and traffic jam forecasts.
    【address】
    PC version (https://www.drivetraffic.jp/)
    Mobile version (http://m.drivetraffic.jp/)
    Smartphone version (http://www.drivetraffic.jp/smp/)
  • NEXCO東日本お客さまセンター
    24時間365日オペレーターが応対いたします。
    【電話番号】
    0570-024-024(ナビダイヤル)または 03-5308-2424
  • ハイウェイテレホン
    電話でリアルタイムの交通情報(5分更新)を24時間365日入手できます。
    【電話番号】
    青森局 017-781-1620
    秋田局 018-826-1620
    盛岡局 019-639-1620
  • 日本道路交通情報センター(JARTIC)
    【アドレス】(http://www.jartic.or.jp/
    【電話番号】
    全国共通情報 050-3369-6666 (携帯電話短縮ダイヤル #8011
    東北地方共通情報 050-3369-6761
  • Highway radio
    Highway radio (AM1620kHz)
    The section that is broadcasting is indicated by the sign on Expressway.
  • Highway Information Terminal
    Wide-area road traffic information is notified on the monitor screen installed in SA / PA.
  • Official Twitter account
    "NEXCO EAST (Tohoku)" (@e_nexco_tohoku) Provides information on Expressway in the Tohoku region.
Expressway renewal project logo image image 2

Expressway renewal project

Now, bring safety and security to the next generation.
NEXCO EAST will work on updating and repairing highways to deliver safety and security to everyone.

8. 8. Scheduled renewal work between Ashiro IC and Kazuno Hachimantai IC

In the fall, we plan to restrict two-way traffic on the In-bound line, which is the opposite of this time. In that case, Yuze PA (Out-bound line) will not be available.

[Scheduled period and section of face-to-face traffic regulation]
Between August and November of Reiwa 3 ... Between Ashiro IC and Kazuno Hachimantai IC (In-bound line) Approximately 15km
* We will inform you about the timing and contents of the regulation.

Image image of detailed map (planned) of traffic restricted section
Image link (external link) to download page of Adobe Acrobat Reader

To view the PDF file, you need the Adobe Systems plug-in software "Acrobat Reader (Japanese version)". If you do not have​​​ Download from here (free)Please use it.