Order construction with a new contract method

-Implementation of pre-bid price negotiation method for steel bridge superstructure work-

February 13, 2008
East Nippon Expressway Co., Ltd.
Tohoku Regional Head Office

NEXCO EAST Tohoku Regional Head Office (Aoba Ward, Sendai City, Regional Head Office President: Mikio Kashima) will place an order for steel bridge superstructure work using the pre-bid price negotiation method.

1 Outline and purpose of pre-bid price negotiation method

The pre-bid price negotiation method requires all bid participants to submit an estimate before bidding, and whether or not the estimate is appropriate for the content of the estimate in order to secure the performance and functions of the construction object. After that, all the bidders and us will perform "technical negotiation" and set the contract limit price that reflects the quotation resubmitted after negotiation, and then bid.

Tender announcement, application, etc., submit quote, technical negotiation, post-negotiation quote, set contract limit price, bid image

2 Target construction

(1) Construction name
Tohoku Expressway Tomiya Junction C ramp bridge (steel superstructure) construction

  • Tohoku Regional Head Office announced on February 13, 2008

(2) Construction site
Grainfield in Tomiya Town, Kurokawa District, Miyagi Prefecture

(3) Construction content
Tohoku Expressway to Tomiya junction under construction in Tohoku Expressway steel superstructure construction work for construction of the bridges that cross bar a.

[Tomiya JCT C ramp bridge]
Bridge length: 64.0m Weight: 170t Factory construction and installation
[Tomiya JCT D ramp bridge]
Bridge length: 63.9m Weight: 220t Construction only
[Sendai-Hokubu Road Main Bridge]
Bridge length: 64.5m Weight: 230t Construction only

(4) Construction period
540 days

3 Reasons for selecting the pre-bid price negotiation method

In this construction, it is necessary to carry out the construction under special construction conditions such as erection of bridges together with the suspension of traffic on the Tohoku Expressway Previous price negotiation method".