Expressway renewal project
[E8] Hokuriku Expressway (Out-bound line) Meitachi Tanihama IC ⇒ Joetsu JCT Notice of night traffic closure and day-night continuous lane regulation (5th report)
- Corporate Top
- Press Room
- Press Release Niigata office
- [E8] Hokuriku Expressway (Out-bound line) Meitachi Tanihama IC ⇒ Joetsu JCT Notice of night traffic closure and day-night continuous lane regulation (5th report)
The latest regulatory information is DraTra Please see.
October 9, 2018
East Nippon Expressway Co., Ltd.
Niigata office
NEXCO EAST Niigata branch (Niigata city Chuo Ward)E8 From October 2017, tunnel reinforcement work has been carried out between the Meitetsu Tanihama Interchange (IC) and Joetsu Junction (JCT) on the Hokuriku Expressway (Out-bound line).
This time, as the 5th report, we will inform you about the night traffic closure in early November.
We apologize for the inconvenience to our customers, but we ask for your understanding and cooperation as it is necessary for the safe and comfortable use of the Expressway.
Route | Hokuriku Expressway |
---|---|
section | Meitetsu Tanihama IC-Joetsu JCT (Out-bound line) |
Implementation period | [1] Closing at night ・ Tuesday, November 6, 2018-Friday, November 9, 2018 [4 days] [2] Day and night continuous lane regulation(Preliminary days) Monday, November 12th, Tuesday, November 13th ・ Under implementation-November 14, 2018 (Wednesday) |
Time | [1] From 20:00 to 6:00 the next morning, [2] 24 hours all day |
Construction content | Tunnel reinforcement work |
Remarks | * The regulation period / time may be changed or canceled depending on the weather and construction progress. |
Closed section
Closing period
- Regarding adjustment of transit charges due to suspension of traffic, Attachment 1 [PDF: 83KB] Please confirm.
- NEXCO EAST's road traffic information providing services etc.,Attachment 2 [PDF: 131KB] Please confirm.
- Regarding the schedule of nighttime closing etc. of the adjacent section scheduled at the same time, Attachment 3 [PDF: 128KB] Please confirm.
Outline of tunnel reinforcement work
Tunnel reinforcement work is a work to install an invert (a lining part that is finished in an inverted arch on the bottom of the tunnel) against the increase in earth pressure around the tunnel, increasing the proof stress of the tunnel, It has the effect of preventing deformation.
Tunnel reinforcement work (other cases)
Lane control methods
Expressway renewal project
NEXCO EAST will work on updating and repairing highways to deliver safety and security to everyone.
[Detailed information on Expressway renewal project]
Search for "Fast Renewal" or Special website Please check.
To view the PDF file, you need the Adobe Systems plug-in software "Acrobat Reader (Japanese version)". If you do not have Download from here (free)Please use it.