Nagano Expressway Azumino IC-Asagi IC (upper and lower lines)
Notice of two-way traffic regulation due to bridge renewal construction

67 days from May 9 (Tue) to July 14 (Fri)
~We will implement a Expressway renewal project in Nagano~

  • Corporate Top
  • Press Room
  • Press Release Kanto Regional Head Office
  • Nagano Expressway Azumino IC-Asagi IC (upper and lower lines) Notice of face-to-face traffic restrictions due to bridge renewal work

The latest regulatory information isDraTraPlease see.

Apr. 10, 2017
East Nippon Expressway Co., Ltd.
Nagano Management Office

Expressway renewal project Image 1

NEXCO EAST Nagano Management Office (Nagano City, Nagano Prefecture) implements face-to-face traffic restrictions accompanying renewal construction of aged bridges between Nagano Chomei Azumino Interchange (IC) and Toba IC (Upper and Lower Line) I will.

The construction to be carried out this time is a construction to replace the reinforced concrete floor slab with a new floor slab at the (Out-bound line) of the Onikumabashi, which is located between Azumino IC of Nagano Expressway IC of Asagi IC. We will regulate the two-way traffic.

During the construction period, it is expected that there will be congestion and congestion on the Expressway, especially on holidays (peak hours 17:00 to 18:00) with a maximum of 3 km on the In-bound line and a maximum of 2 km on the Out-bound line. During construction Homepage for construction, Or the traffic congestion forecast will be posted on websites such as DraPla so please refer to it when using the Expressway.

We ask for your understanding and cooperation as it is necessary to use the Expressway safely and comfortably.

1 construction section

Nagano Expressway Azumino IC-Asagi IC (upper and lower lines)

Image image of construction section

2 Traffic regulation period and congestion forecast

(1) Regulation Period Tuesday, May 9, 2017 - Friday, July 14 (67 days)

Image of regulation period

  • We will continue to work on weekends and holidays day and night.
  • The construction period may change depending on the weather and work progress.

(2) Congestion Forecast

During the construction period, we anticipate the occurrence of traffic jams, mainly on weekends and holidays. Especially on holidays (peak hours from 17:00 to 18:00), In-bound to 3km of traffic can be expected on the up line and up to 2km on the Out-bound line.

Image of traffic congestion prediction

3 Traffic restrictions

In the floor slab replacement work, we will reduce the section of each two lanes of up and down lanes to one lane and implement face-to-face traffic regulation to concentrate on Out-bound lanes. For the first few days at the start and end of the construction period, overtaking lane restrictions will be imposed on the upper and lower lanes in preparation for switching to two-way traffic regulation.

Image of traffic restrictions

4 Construction overview

Located between Nagano Expressway Azumino IC and Asagi IC, Kunikumabashi is a steel 4-span continuous plate girder bridge (197m long) that crosses over the Kunikuma dam. It has been 24 years since it opened in 1993. ..

During this period, the concrete cracks and deterioration of the concrete floor slabs and rust on the reinforcing bars were caused by minute cracks caused by the increase in wheel load due to the increase in size of the vehicle and the salt content contained in the antifreeze agent sprayed during the winter season. It is necessary to carry out plate replacement work.

In order to replace the concrete slab part of the bridge, it is necessary to block the Out-bound line part, so the construction will be done with the two lanes on the In-bound line side as one-way operation with one lane each up and down.

Main work contents

By replacing the existing deteriorated concrete slab with a new concrete slab, it will be transformed into a safe and comfortable Expressway.

Image image of the contents of the main construction

Image of [Removal of concrete floor slab]
[Removal of concrete floor slab]
Image of [Installation of new concrete slab]
[Installation of new concrete slab]
Image of [Construction of new concrete floor slab completed]
[Completion of new concrete floor slab]

*The photo is an example of floor slab replacement work at the Kunikumabashi (In-bound line) that was carried out in the fall of 2016.

5 How to obtain traffic information

(1) Road traffic information available before going out

  • Kunikumabashi floor slab replacement work website
    (Provides the time required to pass the construction section, traffic congestion prediction during the construction period, construction outline, detour information, etc.)
  • NEXCO EAST Customer Center
    (Listen to customers' voices 24 hours a day, 365 days a year)
    Navi dial
    : 0570-024-024
    (24 hours operator support)
    TEL
    03-5338-7524
    (PHS、IP電話のお客さま)
  • For the latest regulatory information, see DraTra "Please refer to the.
  • NEXCO EAST Road Traffic Information Site "Dora Tora"
    (Provides traffic information for Expressway nationwide)
    [PC]
    [Mobile] http://m.drivetraffic.jp/
  • ハイウェイテレホン
    (5分毎に更新される交通情報を24時間提供)
    前橋局 027-252-1620
    長野局 026-278-1620
    (携帯電話・PHS短縮ダイヤル#8162
  • 日本道路交通情報センター(JARTIC)の道路交通情報
    全国共通ダイヤル 050-3369-6666(携帯短縮ダイヤル#8011
    ※全国どこからでも最寄りの情報センターに接続します。
    ※PHS、IP電話など一部の電話からはご利用できません。
    全国・関東甲信越情報050-3369-6600
    インターネット

(2) Road traffic information available during driving

  • Road information board
  • Highway radio (AM1620kHz)
    The highway radio section is indicated by signs on the Expressway.
  • Highway Information Terminal
    Wide-area road information is provided in an easy-to-understand manner on the monitor screens installed in SA / PA.
  • Twitter's official account "NEXCO EAST(Kanto)" (@e_nexco_kanto ) Also delivers information.
Expressway renewal project 2

Expressway Renewal project
Now, bring safety and security to the next generation.
NEXCO EAST, in order to deliver safety and security to everyone,
Expressway We will work on the update and repair business.

Image link (external link) to download page of Adobe Acrobat Reader

To view the PDF file, you need the Adobe Systems plug-in software "Acrobat Reader (Japanese version)". If you do not have​​​ Download from here (free)Please use it.