Tateyama Expressway Futtsu center IC ~ Futtsu-Tateyama Road for the night closed to traffic between the Tomiura IC
- Corporate Top
- Press Room
- Press Release Kanto Regional Head Office
- Tateyama Expressway Futtsu center IC ~ Futtsu-Tateyama Road for the night closed to traffic between the Tomiura IC
October 11, 2006
East Nippon Expressway Co., Ltd.
Kanto Regional Head Office
NEXCO EAST Kanto Regional Head Office (Taito-ku, Tokyo, Regional Head Office length: Hirozo Saeki), the Tateyama Expressway Futtsu center (Futtsu center) Interchange (IC) ~ Futtsu Takeoka (Futtsu Takeoka) IC and between the Futtsu-Tateyama Road Futtsu There will be night traffic closures between the Futtsutakeoka and Tomiura ICs for road maintenance work, facility maintenance inspections and additional lane installation work.
1 All-day lane regulation work section and date and time
(1) Section
Vertical line between Futtsu Chuo IC and Futtsu Takeoka IC on the Tateyama Expressway (extension 7.5km)
Futtsu-Tateyama Road Futtsu Takeoka IC-Tomiura IC vertical line (extension 19.2km) 26.7km in total
(2) Date and time
Wednesday, October 25, 2006 Thursday, October 26, 2006
2 nights from 9pm each night (9 hours)
*Access to the Furari Highway Oasis (up and down) will be closed from 20:30.
In case of stormy weather, it will be postponed to the next day.
In case of stormy weather, the decision on whether or not to close at night will be made at 16:00 pm on the day of the implementation.
Inquiries regarding implementation decisions will be handled by the office below.
NEXCO東日本(株)関東支社 市原管理事務所
TEL.0436-21-0091(代表)
(受付時間 / 平日9:00~17:20)
※但し、工事期間中は随時受付いたします
2 Construction overview
Tateyama Expressway of Futtsu center IC ~ Futtsu Takeoka IC and Futtsu-Tateyama Road of Futtsu Takeoka IC ~ Tomiura between the IC has become an extension 26.7km in the two-lane expressway. About 35% (about 9.2 km) of tunnels in this section, so that customers can use it safely, we regularly inspect tunnel emergency equipment and lighting equipment, replace lamps, repair road damage and provide traffic safety. Equipment maintenance and inspection are required.
In addition, between the Konan Toyama IC and Tomiura IC, additional lane installation work is being carried out to improve runnability, and safety measures such as temporary protection fences and rockfall protection fences will be implemented.
Since this section is a provisional two-lane road, most of the traffic restrictions in construction work are alternate traffic restrictions on one side, so as a way to minimize the impact on customers, we will close the road at night on weekdays when traffic volume is low, The work is carried out intensively and efficiently.
Contents of construction [PDF: 84KB]
3 detour
If you use this section when the road is closed, general national road 127 will be the detour route.
The time required between Futtsu Chuo IC and Tomiura IC is about 25 minutes, but if you use the detour route, the time required will be about 55 minutes, so if you use this section, please be sure to leave time.
Detour status map
Attachment (About closed information) [PDF: 11KB]
To view the PDF file, you need the Adobe Systems plug-in software "Acrobat Reader (Japanese version)". If you do not have Download from here (free)Please use it.