Emergency inspection of tunnel ceiling panels in NEXCO EAST (interim bulletin)

  • Corporate Top
  • Press Room
  • Press Release Headquarters
  • Emergency inspection of tunnel ceiling panels in NEXCO EAST (interim bulletin)

December 7, 2012
East Nippon Expressway Co., Ltd.

NEXCO EAST is About emergency inspection of tunnel ceiling board We carried out an emergency inspection work on the 11 target tunnels based on the instructions of "," and finished the work onsite today.

No damage that hinders running has been found.

[Reference] Tunnel where emergency inspection work was performed

AdminRoute nameTunnel nameUp and downtunnel
Extension
(Km)
Of which ceiling plate
Installation extension
(Km)
Remarks
NEXCO East JapanKan-Etsu ExpresswayKanetsu tunnelIn-bound line11.10.17 
Out-bound line10.90.15 
Hokuriku ExpresswayNou tunnelOut-bound line3.00.02 
Takamine tunnelOut-bound line3.10.02 
Child ignorance tunnelIn-bound line4.60.05 
City swing tunnelOut-bound line3.30.05 
Aqua LineTokyo Bay Aqua TunnelIn-bound line9.60.3 
Out-bound line9.60.3 
Nagano RoadTachitoge tunnelOut-bound line3.60.02 
Joshin-Etsu ExpresswayGorigamine tunnelIn-bound line4.50.04 
Happu-san tunnelOut-bound line4.50.05 
Taro mountain tunnelIn-bound line4.30.02 
Ken-O RoadSugawa TunnelIn-bound line2.40.04 
Out-bound line2.40.04 
(11 tunnels: 14 tubes, target length 1.3km)