Large supplies (water storage tanks) associated with the Fukushima Daiichi Nuclear Power Station accident response
Expressway traffic planning for low-speed vehicles for transportation
- Corporate Top
- Press Room
- Press Release Headquarters
- Large supplies (water storage tanks) associated with the Fukushima Daiichi Nuclear Power Station accident response
(Added on July 7, 2011)
The low-Expressway traffic for transportation of goods (storage tanks) by large trailers, which was carried out from June 16, was completed on Wednesday, July 6.
Thank you for your cooperation.
June 14, 2011
East Nippon Expressway Co., Ltd.
In response to the Fukushima Daiichi Nuclear Power Plant accident, Tokyo Electric Power Co., Inc. 3 To transport the water tank, large trailers form a line as shown below, and pass through the Expressway at a low speed (about 50 km/h).
When platooning large trailers, traffic restrictions such as overtaking and temporary closure of the entrance to the toll gate are planned, and congestion is expected. It is also planned that multiple large trailers will be parked in the service area and parking area at the same time in order to mitigate long-term customer follow-up driving.
We apologize for the inconvenience, but we ask our customers to be careful when traveling and to have enough time to travel.
1-passing vehicle (low-speed vehicle) (*1)
Large trailers (6 units) for transporting large materials (water storage tanks) and trains for guided vehicles (total length of about 500 m)
2 traffic period (*2)
From Thursday, June 16, 2011 to early July (every day, midnight)
3 Passage sections/Estimated transit time
Road name | Passing section (*3) | Estimated transit time (*4) | ||
---|---|---|---|---|
Tohoku Expressway | Kanuma interchange | → | Tochigi Tsuga Junction | 23:30~0:30 |
Kita-Kanto Expressway | Tochigi Tsuga Junction | → | Tomobe Junction | 0:30~2:00 |
Joban Expressway | Tomobe Junction | → | Iwaki Junction | 2:00~4:30 |
Joban Expressway | Iwaki Junction | → | Hirono Interchange | 4:30~5:30 |
4 Please note
- The number of passing vehicles is subject to change. (*1)
- The traffic period may be canceled or extended depending on the work process at the nuclear power plant (*2).
- The traffic section may change depending on traffic conditions. (*3)
- The estimated transit time is a guide. (※Four)
- In addition to this formation, 100m 3 There are plans to pass vehicles that carry water tanks, but there are no traffic restrictions.
- Before using, please visit our website "Drive traffic (DraTra) Please check the latest traffic conditions by "."