About the situation of the Expressway accompanying the earthquake with the epicenter off Miyagi Prefecture
- Corporate Top
- Press Room
- Press Release Headquarters
- About the situation of the Expressway accompanying the earthquake with the epicenter off Miyagi Prefecture
April 8, 2011
As of 14:00
East Nippon Expressway Co., Ltd.
We would like to inform you about the damage situation of Expressway in NEXCO EAST business area due to the earthquake off Miyagi prefecture around 23:32 on April 7, 2011.
Since the earthquake this time, the lines and sections where the shaking was large were closed, emergency inspections were carried out, and the closed roads were sequentially released from the sections where safety was confirmed.
The main damages that have been identified to date are 44 locations on four routes and about 77 kilometers, and we are working hard to complete the emergency recovery.
1 Currently closed sections
Road name | section | By vertical line | Remarks |
---|---|---|---|
Tohoku Expressway | Furukawa IC-Misawa IC | Up and down | |
Sendai-Hokubu Road | Rifu JCT-Rifu Shirakashidai IC | Up and down | Canceled on April 8 at 14:00 |
Sanriku Expressway | Sendai Kohoku IC-Rifuchu IC | Up and down | Rifu JCT-Rifuchu IC is closed at 14:00 on April 8th |
Sendai-Tobu Road | Sendai East IC-Sendai Kohoku IC | Up and down |
2 Summary of major damage
In the above-mentioned closed section, 44 major damages such as steps (up to approximately 20 cm) or cracks (cracks) on the road surface have been confirmed.
Also, of these 44 locations, the embankment deformation (the embankment on the road shoulder collapsed for a height of about 20 m and a length of about 30 m) at the embankment structure between the Tohoku Expressway Hiraizumi Maesawa IC and Mizusawa IC (In-bound line). has occurred, Sendai-Tobu Road in the bridge section between Sendai Higashi IC ~ Sendai Kohoku IC (top and bottom lines), the bridge girder is a deviation about 5cm in the horizontal direction, we step occurs in the road surface of the joint.
Tohoku Expressway Hiraizumi Maesawa IC-Misawa IC (In-bound line)
Sendai-Tobu Road Sendai East IC-Sendai Kohoku IC (upper and lower lines)
Sendai-Tobu Road Sendai East IC-Sendai Kohoku IC (upper and lower lines)
3 Expected completion of emergency recovery
Tohoku Expressway Furukawa IC-Ichinoseki IC and Sanriku Expressway Sendai Kohoku IC-Rifu JCT between the evening of today, Sendai Tobu Sendai-Tobu Road Sendai East IC-Sendai Kohoku IC and Tohoku Expressway Ichinoseki IC-Hiraizumi Maesawa IC-Tohoku Expressway between the Hiraizumi Maezawa IC ~ Mizusawa IC Out-bound for the line, with the aim tomorrow April 9, the morning each, we aim to complete as soon as possible.
In addition, the In-bound line between Hiraizumi Maesawa IC and Mizusawa IC, which was relatively damaged, is expected to require several days for emergency restoration, but we aim to complete it as soon as possible.