Joshin-Etsu Expressway Yokogawa Service Area (Out-bound Line)
Notice of construction status

You are viewing a page with old information.
Since the latest information is posted,
"News from NEXCO EAST Please check from.

October 25, 2016
East Nippon Expressway Co., Ltd.
Saku Management Office

NEXCO EAST Saku Management Office (Saku City, Nagano Prefecture) is working to make the parking lot in the Joshin-Etsu Expressway Yokogawa Service Area (Out-bound line) barrier-free and pavement repair work in order to use the rest facility more safely and comfortably. It is being carried out.

We will inform you of the current construction status.

We apologize for the inconvenience and inconvenience to our customers, but we appreciate your understanding and cooperation.

You can use the restroom and commercial facilities as usual.

1 construction period

Yokogawa service area Out-bound line: From early September 2016 to late December 2016
No work will be done on Saturdays, Sundays and public holidays.

  • In-bound line is scheduled from early January 2017 to early May 2017.
    Details will be announced later.

2 Construction site

Yokogawa, Matsuida Town, Annaka City, Gunma Prefecture

Image image of construction site

3 Construction details

We will carry out barrier-free construction of the parking lot. During the construction period (weekdays), divide the construction range (Steps 1-11) Construction will be carried out sequentially with continuous day and night restrictions.

Image image of construction contents
Construction step blockScheduled construction periodConstruction contentRemarks
step 1-Waterway constructionComplete
Step 2-Pavement workComplete
Step 3From October 24, 2016 to October 28, 2016Pavement workplans
Step 4October 31, 2016-November 4, 2016Pavement workplans
Step 5November 7, 2016-November 11, 2016Pavement workplans
Step 6From November 14, 2016 to November 18, 2016Pavement workplans
Step 7From November 21, 2016 to November 25, 2016Pavement workplans
Step 8From November 28, 2016 to December 2, 2016Pavement workplans
Step 9December 5, 2016-December 9, 2016Pavement workplans
Step 10December 12, 2016-December 16, 2016Pavement workplans
Step 11From December 19, 2016 to December 22, 2016Pavement workplans
Image image of barrier-free parking
Image of making parking lots barrier-free
Image image of pavement repair work
Image of pavement repair work

4 Facilities available during construction

Due to construction work, some parking spaces are restricted, but the following facilities are available.

  • Bathroom
  • Commercial facilities (shops, snack corners, restaurants, etc.)