[E4] Tohoku Expressway between Kazuno Hachimantai IC and Kosaka IC
Implementation of all-day face-to-face traffic regulation due to bridge renewal work

  • Corporate Top
  • Press Room
  • Press Release Tohoku office
  • [E4] Tohoku Expressway Kazuno Hachimantai IC-Kosaka IC Ryo Bridge Implementation of all-day face-to-face traffic regulation due to renewal work

The latest regulatory information isDraTraPlease see.

PDF version [PDF: 884KB]

Expressway renewal project logo image image 1

July 15, 4th year of Reiwa
East Nippon Expressway Co., Ltd.
Tohoku Regional Head Office Aomori management office

NEXCO EAST Aomori Management Office (Aomori City, Aomori Prefecture) has deteriorated at the Jinba Bridge located between the E4 Tohoku Expressway Towada Interchange (IC) and Kosaka IC. Due to the construction to replace the reinforced concrete floor slab with a new floor slab, the section of each of the two lanes on the upper and lower lanes will be reduced to one lane each, and the all-day lane regulation will start on Thursday, August 18, and all-day two-way traffic will be concentrated on one side. Regulations will be enforced from Monday, August 29th.
We apologize for any inconvenience caused to our customers, but if you drive on the section, please try to drive more safely and leave with plenty of time.
Renewal work is necessary to use the Expressway safely and securely. We will do our best to minimize the inconvenience to our customers, so we ask for your understanding and cooperation.

◆Construction image photograph

[Surface traffic regulation status] photo
[Restrictions on face-to-face traffic]
[Old floor slab removal status] photo
[Removal of old slabs]
[New floor slab installation status] photo
[New slab installation status]

1. 1. Traffic regulation section

Between Tohoku Expressway Kazuno Hachimantai IC and Kosaka IC (upper and lower lines)

Image of position map
Image image of construction section

2. Traffic regulation period

  1. Traffic regulation period
    Reiwa 4th August 18th (Thursday) -November 8th (Tuesday) (83 days)
Image of traffic regulation period (August)
Image of traffic regulation period (September)
Image of traffic regulation period (October)
Image of traffic regulation period (November)

【Usage Guide】
All-day lane regulation implementation date (23 days)
All-day face-to-face traffic regulation implementation date (60 days)

  • Saturday, Sunday and public holidays are also regulated throughout the day.
  • The regulation period may change depending on the progress of construction work.

3. 3. Traffic regulation contents

For the floor slab replacement work, the sections of each of the two lanes on the upper and lower lines will be consolidated into one lane, and two-way traffic restrictions will be enforced throughout the day. Before and after the two-way traffic regulation period, we will implement all-day lane regulation for up and down lanes as a preparatory work for switching lanes.

◆Image of lane regulation and two-way traffic regulation

Image of lane regulation
Image of face-to-face traffic regulation

Four. Construction content

Approximately 36 years have passed since the opening of the Jinba Bridge between Towada C and Kosaka IC on the Tohoku Expressway, and fine cracks and salt content when spraying antifreeze agents during the winter season due to repeated wheel loads due to the increase in vehicle size. As a result, the concrete deck has deteriorated and the reinforcing bars have rusted, so it is necessary to carry out drastic anti-aging work.
By replacing the deteriorated existing concrete deck with a new deck, it will be reborn as a safe and comfortable Expressway.

◆ Construction overview

Image image of construction outline

Five. Request when using

  1. The construction section will be restricted to face-to-face traffic throughout the day for approximately 5.4km. We do not anticipate the occurrence of traffic jams, but when using the section, please try to drive safely and go out with plenty of time.
  2. Since the driving lane and shoulders are narrow in the two-way traffic restricted section, please observe the regulated speed when driving, secure the inter-vehicle distance, and be careful about rear-end collisions. In addition, the lanes will change significantly before and after the two-way traffic regulation section, so please follow the local information signs.
  3. Vehicles for construction work may enter and leave the area around the construction site, so please be careful when traveling ahead.
  4. During the construction period, we will provide traffic congestion information using LED information boards, provide construction regulation information using road information boards and road signs, and call attention to driving safely. Please check this information before driving and drive safely.

◆ Photograph of information provided around the construction site

[LED information board] photo
[LED information board]
[Road information board] photo
[Road information board]
[Construction control material] photo
[Construction regulation materials]

6. Efforts to minimize inconvenience to customers due to regulations

[Adoption of precast products for the purpose of shortening the construction period and improving quality]
By adopting the floor slab of precast products, the regulation period is shorter than usual.
* What is precasting? Pre-manufacturing products at factories, etc.

[Advance notice of construction regulations and traffic jam information by construction website, signboard, etc.]
We will inform you in advance of the regulation contents by means of the construction website, signboards, banners, etc.

[Notice image] * This is a public relations material for the renewal work carried out in the past year.

◆ HP dedicated to construction

Image image of HP for construction only

◆ Stand sign

Photo of the signboard

◆ Banner

Banner photo

7. How to obtain traffic information

  • "DraPla", a site full of useful information on Expressway nationwide
    [Address] https://www.driveplaza.com/
  • Expressway traffic information service "Drive Traffic (DraTra)"
    【address】
    Real-time information https://www.drivetraffic.jp/
    Construction regulation information https://www.drivetraffic.jp/construction-regulation
  • NEXCO東日本お客さまセンター
    24時間365日オペレーターが応対いたします。
    【電話番号】
    0570-024-024(ナビダイヤル) または 03-5308-2424
  • 日本道路交通情報センター(JARTIC)
    【アドレス】 https://www.jartic.or.jp/
    【電話番号】
    全国共通ダイヤル 050-3369-6666 (携帯短縮ダイヤル #8011
    ※全国どこからでも最寄りの情報センターに接続します。
    東北地方高速情報 050-3369-6761
  • Highway radio
    Highway radio (AM1620kHz)
    The section that is broadcasting is indicated by the sign on Expressway.
  • Highway Information Terminal
    Wide-area road traffic information is notified on the monitor screen installed in SA / PA.
  • Official Twitter account
    "NEXCO EAST (Tohoku)" (@e_nexco_tohoku) Provides information on Expressway in the Tohoku region.
Expressway renewal project logo image image 2

Expressway renewal project
Now, safety and security are passed on to the next generation.
NEXCO EAST will work on a large-scale renewal and repair business of Expressway in order to provide you with safety and security.
Or search for "high-speed renewal".

The NEXCO EAST Group has positioned the period from 2021 to 2025 as "a period that contributes to the achievement of the SDGs and transforms into a new future society," and is making various efforts.
We believe that this "renewal work" initiative will contribute to the SDGs goals No. 8, 9, and 11 as business activities that lead to the development of safe, secure, and reliable infrastructure.

Image image of SUSTAINABLE DEVELOPMENT GOALS logo and No. 8 logo for economic growth that is rewarding to work, No. 9 logo for creating a foundation for industry and technological innovation, and No. 11 logo for community development that allows people to continue living.