[E4] Between Shirakawa IC and Sukagawa IC on the Tohoku Expressway
Implemented all-day face-to-face traffic regulation due to bridge renewal work
- Corporate Top
- Press Room
- Press Release Tohoku office
- [E4] Tohoku Expressway Shirakawa IC-Sukagawa IC Bridge Ryo Implemented all-day face-to-face traffic regulation due to renewal work
The latest regulatory information isDraTraPlease see.
April 9, 3rd year of Reiwa
East Nippon Expressway Co., Ltd.
Tohoku Regional Head Office Koriyama management office
NEXCO EAST Koriyama Management Office (Koriyama City, Fukushima Prefecture) has an aging reinforced concrete floor at the No. 1 Kumatogawa Bridge located between the E4 Tohoku Expressway Due to the construction to replace the slab with a new floor slab, the section of 2 lanes on each of the upper and lower lines will be reduced to 1 lane each, and face-to-face traffic restrictions will be enforced all day from May 16 (Sun).
Since the number of lanes that can be driven will be reduced from two lanes to one lane due to the construction work, traffic congestion is expected on holidays near the construction site between the Shirakawa IC and Sugagawa IC on Tohoku Expressway
We apologize for any inconvenience caused to our customers, but if you drive in the section, please try to drive more safely and leave with plenty of time. In addition, if you are planning to use the section on a holiday Joban Expressway or general road, changing the outing time, or using public transportation.
Renewal work is necessary to use the Expressway We will do our best to minimize the inconvenience to our customers, so we ask for your understanding and cooperation.
◆Construction image photograph
1. 1. Traffic regulation section
Tohoku Expressway Shirakawa IC-Sukagawa IC (upper and lower lines)
* Yabuki IC can be used.
2. Traffic regulation period and traffic congestion forecast
(1) Traffic regulation period
May 11th (Tuesday) -June 25th (Friday) (46 days)
【Usage Guide】
Day and night continuous lane regulation implementation date (10 days)
All-day face-to-face traffic regulation implementation date (36 days)
- Construction will be done on Saturdays and Sundays.
- The lane regulation date and face-to-face traffic regulation date may change depending on the progress of construction.
(2) Congestion forecast
During the construction period, it is predicted that there will be a maximum of 5km of traffic on holidays. Congestion time is estimated to be around In-bound line and 9:00 to 11:00 on the Out-bound Joban Expressway and general roads, change of outing time or use of public transportation Please consider it.
3. Traffic restrictions
For the floor slab replacement work, the section of each of the two lanes on the upper and lower lanes will be reduced to one lane each, and will be consolidated on one side to implement two-way traffic restrictions throughout the day. During the first and last few days of the construction period, lane restrictions will be applied to both the upper and lower lanes as a preparatory work for switching lanes.
◆Image of lane regulation and two-way traffic regulation
Four. Construction content
Approximately 48 years have passed since the opening of the No. 1 Kumatogawa Bridge, which is located between the Yabuki IC and Sukagawa IC on the Tohoku Expressway Due to the salt content of the concrete floor slab and rust on the reinforcing bars, it is necessary to carry out drastic anti-aging work.
By replacing the deteriorated existing concrete floor slab with a new floor slab, it will be reborn as an Expressway
◆ Construction overview
Five. Request when using
- Face-to-face traffic will be restricted throughout the construction section for approximately 3.3km. A decrease from the two lanes of the status quo to one lane, at the beginning of the construction work place, because the traffic jam on the order of up to 5km have been predicted, Joban Expressway detour to and general road, for the use of the change or public transportation going out time Please consider it.
- Since the driving lane and shoulders are narrow in the two-way traffic restricted section, please observe the regulated speed when driving, secure the inter-vehicle distance, and be careful about rear-end collisions. In addition, the lanes will change significantly before and after the two-way traffic regulation section, so please follow the local information signs.
- Vehicles for construction work may enter and leave the area around the construction site, so please be careful when traveling ahead.
- During the construction period, we will provide traffic congestion information using LED information boards, provide construction regulation information using road information boards and road signs, and call attention to driving safely. Please check this information before driving and drive safely.
◆ Photograph of information provided around the construction site
6. Efforts to minimize inconvenience to customers due to construction work
[Adoption of precast products for the purpose of shortening the construction period and improving quality]
By adopting a precast PC floor slab, the construction period is shortened and the regulation period is shortened.
* Precast is to manufacture products in advance at factories, etc.
[Advance notice of construction regulations and traffic jam information by TV commercials, radio commercials, newspaper advertisements, etc.]
We will inform you in advance of the regulation contents by TV commercials, radio commercials, newspaper advertisements, etc. mainly in the Tohoku region.
[Notice image] * This is a public relations material for the renewal work carried out in the fall of 2020
◆ TV commercial
◆ Stand sign
◆ Poster
◆ Leaflet
7. How to obtain traffic information
- DraPla", a site full of useful information on Expressway nationwide
【address】
PC version (https://www.driveplaza.com/)
Mobile version (http://m.driveplaza.com/)
Smartphone version (http://www.driveplaza.com/smp/) - Expressway traffic information service "Drive Traffic (DraTra)"
(Https://www.drivetraffic.jp/construction-regulation)
It provides real-time road traffic information.
【address】
PC version (https://www.drivetraffic.jp/)
Mobile version (http://m.drivetraffic.jp/)
Smartphone version (http://www.drivetraffic.jp/smp/) - NEXCO東日本お客さまセンター
24時間365日オペレーターが応対いたします。
【電話番号】
0570-024-024 または 03-5308-2424 - ハイウェイテレホン
電話でリアルタイムの交通情報(5分更新)を24時間入手できます。
【電話番号】
郡山局 024-961-1620
(携帯電話・PHS短縮ダイヤル #8162) - 日本道路交通情報センター(JARTIC)
【アドレス】 http://www.jartic.or.jp/
【電話番号】
全国共通ダイヤル 050-3369-6666 (携帯短縮ダイヤル #8011)
※全国どこからでも最寄りの情報センターに接続します。
福島情報 050-3369-6607
東北地方高速情報 050-3369-6761 - Highway radio
Highway radio (AM1620kHz)
The section that is broadcasting is indicated by the sign on Expressway. - Highway Information Terminal
Wide-area road traffic information is notified on the monitor screen installed in SA / PA.
- Official Twitter account "NEXCO EAST (Tohoku)" (@E_nexco_tohoku) Also delivers information.
Expressway renewal project
Now, safety and security are passed on to the next generation.
NEXCO EAST will work on a large-scale renewal and repair business of Expressway in order to provide you with safety and security.
To view the PDF file, you need the Adobe Systems plug-in software "Acrobat Reader (Japanese version)". If you do not have Download from here (free)Please use it.