Introduced different types of construction work on Expressway renewal project
- Corporate Top
- Press Room
- Regular press conference materials
- 2018
- Introduced different types of construction work on Expressway renewal project
Introducing work of dissimilar construction in the Expressway renewal project
-Tohoku Tohoku Expressway Towada Jurisdiction Expressway Renewal Contract-
August 1, 2018
East Nippon Expressway Co., Ltd.
NEXCO EAST (Chiyoda-ku, Tokyo) contracts for the construction (different work construction) to consolidate multiple works under one traffic regulation in order to efficiently implement the Expressway renewal project business.
By planning such construction, we expect repeated reductions in traffic regulations between the same interchanges (ICs) and efficient construction management and safety management by construction contractors ( Attachment [PDF: 314KB] reference).
2018 fiscal year, "Tohoku Expressway Towada (Towada) tube Expressway is scheduled for contract renewal construction" (bid announcement expected early August). The outline of construction work is as follows.
1 Construction overview
Within Towada Administration Office (66.1km between Tohoku Expressway Ashiro IC and Ikarigaseki IC), multiple contracts were contracted as one construction. (Contracted for multiple "bridge floor plate replacement work" and "tunnel repair work" at the same time)
Construction name | Tohoku Expressway Towada Jurisdiction Expressway Renewal Construction |
---|---|
Construction site | Tohoku Expressway (Self) Koyanagida, Hachimantai City, Iwate Prefecture [Ashiro IC] (To) Ikarigaseki, Hirakawa City, Aomori Prefecture [Ikarigaseki IC] |
Scheduled bidding period (Construction period) |
2018/3 / quarter contract plan (39 months: 1,170 days) |
Construction quantity | Floor slab replacement approx. Two Reinforcement of lining about 74.0 thousand m Two Tunnel cavity injection About 4.5 thousand m Three |
Bid method | Comprehensive evaluation successful bid method (Technical proposal evaluation type Proposal type I [Construction system confirmation type combined use]) |
Participation requirements Eligibility |
Single or specified construction work joint venture Bridge repair work, civil engineering repair work |
2 Construction location map, etc.
- During the construction period (about 3 years), we plan to implement traffic regulation and construction sequentially.