Introduced different types of construction work on Expressway renewal project

Introducing work of dissimilar construction in the Expressway renewal project

-Tohoku Tohoku Expressway Towada Jurisdiction Expressway Renewal Contract-

Image of Renewal

August 1, 2018
East Nippon Expressway Co., Ltd.

NEXCO EAST (Chiyoda-ku, Tokyo) contracts for the construction (different work construction) to consolidate multiple works under one traffic regulation in order to efficiently implement the Expressway renewal project business.

By planning such construction, we expect repeated reductions in traffic regulations between the same interchanges (ICs) and efficient construction management and safety management by construction contractors ( Attachment [PDF: 314KB] reference).

2018 fiscal year, "Tohoku Expressway Towada (Towada) tube Expressway is scheduled for contract renewal construction" (bid announcement expected early August). The outline of construction work is as follows.

1 Construction overview

Within Towada Administration Office (66.1km between Tohoku Expressway Ashiro IC and Ikarigaseki IC), multiple contracts were contracted as one construction. (Contracted for multiple "bridge floor plate replacement work" and "tunnel repair work" at the same time)

Construction name Tohoku Expressway Towada Jurisdiction Expressway Renewal Construction
Construction site Tohoku Expressway
(Self) Koyanagida, Hachimantai City, Iwate Prefecture [Ashiro IC]
(To) Ikarigaseki, Hirakawa City, Aomori Prefecture [Ikarigaseki IC]
Scheduled bidding period
(Construction period)
2018/3 / quarter contract plan
(39 months: 1,170 days)
Construction quantity Floor slab replacement approx. Two
Reinforcement of lining about 74.0 thousand m Two
Tunnel cavity injection About 4.5 thousand m Three
Bid method Comprehensive evaluation successful bid method
(Technical proposal evaluation type Proposal type I [Construction system confirmation type combined use])
Participation requirements
Eligibility
Single or specified construction work joint venture
Bridge repair work, civil engineering repair work

2 Construction location map, etc.

Image images of main construction points and regulatory points
  • During the construction period (about 3 years), we plan to implement traffic regulation and construction sequentially.
Photos of Kamedayama TN and Kosakagawa Bridge