May 13, 4th year of Reiwa
East Nippon Expressway Co., Ltd.
Niigata Regional Head Office

NEXCO EAST Niigata Regional Head Office (Chuo-ku, Niigata City) E7 Nihonkai-Tohoku Expressway Niigata Airport Niigatakukou Interchange (IC) ~ Arakawa womb I don't know At the IC (upper and lower lines), we will close the road at night due to pavement repair work in the two-way traffic section.
When you go out, please leave with plenty of time, and when you drive, please detour to National Highway No. 7.
We apologize for the inconvenience caused to our customers, but we ask for your understanding and cooperation as it is a closed road necessary for the safe and comfortable use of the Expressway.

Route Nihonkai-Tohoku Expressway up and down line
section (1) Niigata Airport IC-Seiro Shibata IC (2) Seiro Shibata IC-Arakawa wombai IC
Implementation period June 13th (Monday) -June 17th (Friday) [5 nights]
Preliminary day: June 20th (Monday) to 24th (Friday)
June 27th (Monday) -July 8th (Friday) [10 nights]
Preliminary day: July 11th (Monday) to 22nd (Friday)
Time From 20:00 to 6am
  • It will not be held on weekends and holidays at night.
  • Friday night construction will also be carried out until 6:00 the next day (Saturday morning 6:00).
Regulation content Night traffic
Construction content Pavement repair work and maintenance repair work, etc.
Remarks
  • During the closed period of (1), the Toyosaka Service Area (SA) and Toyosaka Smart IC (both up and down lines) cannot be used during the closed hours.
  • Depending on the weather and construction progress, the regulation section / period / time may be changed or canceled.
  • When using, please check the latest information from Attachment-1 [PDF: 107KB] such as services that provide road traffic information of NEXCO EAST.

1. 1. Road closure location map and detour map

(1) Niigata Airport IC-Seiro-Shibata IC (upper and lower lines)
[Closed date and time]
June 13th (Monday) -June 17th (Friday) [5 nights]
From 20:00 to 6:00 the next day

  • Not held on Saturdays and Sundays at night
  • Friday night construction will also be carried out until 6:00 the next day (Saturday morning 6:00).

【Preparation day】
June 20th (Monday) to 24th (Friday)
From 20:00 to 6:00 the next day

  • Toyosaka SA and Toyosaka Smart IC (both up and down lines) cannot be used during closed hours.

(2) Seiro-Shibata IC-Arakawa-Taina IC (upper and lower lines)
[Closed date and time]
June 27th (Monday) -July 8th (Friday) [10 nights]
From 20:00 to 6:00 the next day

  • Not held on weekends and holidays at night
  • Friday night construction will also be carried out until 6:00 the next day (Saturday morning 6:00).

【Preparation day】
July 11th (Monday) to 22nd (Friday)
From 20:00 to 6:00 the next day

Image of closed position map and detour map

2. About detours

It takes about 15 minutes from Niigata Airport IC to Seiro Shibata IC, but it takes about 20 minutes under normal traffic conditions when using National Highway No. 7 (Shinshin Bypass).
It takes about 20 minutes from Seiro Shin-Taina IC to Arakawa-Taina IC, but it takes about 45 minutes under normal traffic conditions when using National Highway No. 7.

  1. Please refer to Attachment-2 [PDF: 174KB] for the transfer fee adjustment due to the traffic closure of the closed section (Niigata Airport IC-Seiro-Shibata IC).
  2. There will be no transfer fare adjustment due to traffic closure in the closed section (Seiro-Shibata IC-Arakawa-Taina IC).

3. 3. Traffic closure implementation period

(1) Niigata Airport IC-Seiro-Shibata IC (upper and lower lines)
June 13th (Monday) to 17th (Friday), 4th year of Reiwa
Every night from 20:00 to 6:00 the next day
[Preliminary day: June 20th (Monday) to 24th (Friday)]

(2) Seiro-Shibata IC-Arakawa-Taina IC (upper and lower lines)
June 27th (Monday) -July 8th (Friday), 4th year of Reiwa
Every night from 20:00 to 6:00 the next day
[Preliminary day: July 11th (Monday) to 22nd (Friday)]

Image of the road closure period
  • Seiro-Shibata IC-Arakawa-Taina IC has many damaged parts and a large amount of repairs, so it is closed for 10 nights. We apologize for the inconvenience, and thank you for your understanding.

Four. Construction overview

We will repair the damaged road surface of Nihonkai-Tohoku Expressway Niigata Airport IC-Arakawa-Taina IC and repair accessories damaged by the accident.

Photo of damaged road surface condition 1
Photo of damaged road surface condition 2
Damaged road surface condition
Photograph of the situation of accessories damaged by the accident 1
Photograph of the situation of accessories damaged by the accident 2
Status of accessories damaged by the accident
Image link (external link) to download page of Adobe Acrobat Reader

To view the PDF file, you need the Adobe Systems plug-in software "Acrobat Reader (Japanese version)". If you do not have​​​ Download from here (free)Please use it.