[E8] Between Nakanoshima Mitsuke IC and Sanjo-Tsubame IC on the Hokuriku Expressway
Notice of all-day face-to-face traffic restrictions due to bridge renewal work

  • Corporate Top
  • Press Room
  • Press Release Niigata office
  • [E8] Notice of all-day face-to-face traffic restrictions due to bridge renewal work between Nakanoshima Mitsuke IC and Sanjo-Tsubame IC on the Hokuriku Expressway

The latest regulatory information isDraTraPlease see.

PDF version [PDF: 2.0MB]

Expressway renewal project logo image image 1

April 16, 3rd year of Reiwa
East Nippon Expressway Co., Ltd.
Niigata Regional Head Office

NEXCO EAST Niigata Regional Head Office (Niigata Chuo-ku) is, E8 Hokuriku Expressway in Kaibami River Kaibamigawa Bridge and Rong Rong Bridge located between Sanjo Tsubame Sanjo swallow IC from Nakanoshima Mitsuke Nakanoshima Mitsuke interchange (IC) , From Saturday, May 15th, we will implement face-to-face traffic restrictions throughout the day for construction to replace the aging reinforced concrete floor slab with a new floor slab.
Under the two-way traffic regulation that will be implemented this time, the number of lanes that can be driven will be reduced from 4 lanes to 3 lanes. Change the number to alleviate traffic jams in the morning and evening. However, during the construction period, traffic congestion is expected mainly on Saturdays, Sundays, and holidays.
We apologize for the inconvenience caused to our customers, but if you drive in the section, please try to drive more safely and leave with plenty of time. In addition, customers who plan to use the section on Saturdays, Sundays, and holidays are requested to detour to Route 8, change the outing time, or use public transportation. For customers who detour to Route 8 on Saturdays, Sundays, and holidays, we will also adjust the charges.
In addition, we are planning to continue the renewal work in the 4th year of Reiwa, and we will inform you of the details again.
Renewal work is necessary to use the Expressway We will do our best to minimize the inconvenience to our customers, so we ask for your understanding and cooperation.

◇ Renewal work image photo

Photo of removal of old floor slab
Removal of old floor slab
Photograph of new floor slab installation
Installation of new floor slab
Photograph of lane switching using the road zipper system
Lane switching using the road zipper system
Photograph of face-to-face traffic regulation status
Face-to-face traffic regulation status
* The photo shows 2-lane operation, but it will be 3-lane operation.

1. 1. Outline of construction (implemented in 3rd year of Reiwa)

Route Hokuriku Expressway
section Nakanoshima Mitsuke IC-Sanjo Tsubame IC Vertical line
Implementation period May 15th (Sat) -July 15th (Thursday), 3rd year of Reiwa
Reiwa 3rd August 25th (Wednesday) -October 27th (Wednesday)
  • We also carry out Saturdays, Sundays, and holidays.
  • The regulation period may change depending on the progress of construction and the weather.
  • For details, see 3. Please see the traffic regulation period and traffic congestion forecast.
Time All day (24 hours)
Construction content Floor slab replacement work
Remarks
  • Lanes and shoulder width will be narrowed during the period.
  • In this construction, face-to-face traffic regulation will be implemented using the road zipper system. Please see Attachment-1 [PDF: 882KB] for details.
  • For the latest regulatory status, please see Attachment-2 [PDF: 63KB], such as services that provide road traffic conditions in NEXCO EAST
  • During the all-day face-to-face traffic regulation period, we will adjust the charges as necessary for customers who detour to Route 8 during some hours on Saturdays, Sundays, and holidays. Please see Attachment-3 [PDF: 454KB] for details.

2. Location map of construction section and regulation image map

Nakanoshima Mitsuke IC-Sanjo-Tsubame IC will be regulated up to about 5.5km.

Image image of the position map of the construction section 1
Image image of the location map of the construction section 2
Processed by Expressway Company based on the Geographical Survey Institute map (Geographical Survey Institute) (https://maps.gsi.go.jp/)

Regulatory image diagram

Image image of regulation image diagram

3. 3. Traffic regulation period and traffic congestion forecast

(1) Traffic regulation period
◇ All-day face-to-face traffic regulation
May 15th (Sat) -July 15th (Thursday), 3rd year of Reiwa
Reiwa 3rd August 25th (Wednesday) -October 27th (Wednesday)
◇ Continuous day and night (all day) lane regulation
May 11th (Tuesday) -May 14th (Friday), July 16th (Friday), August 24th (Tuesday), October 28th (Thursday)
* Even on days when lane restrictions are not enforced, the lane and shoulder width are narrower than in the normal season.

Image of traffic regulation period

(2) Congestion forecast
During the construction period Saturdays, Sundays, and holidays It is predicted that there will be a maximum of 10km of traffic around the area. Congestion is predicted to occur mainly from 7:00 to 12:00 on Out-bound line and In-bound Please detour to Route 8, change your outing time, or use public transportation.

  • During the all-day face-to-face traffic regulation period, during some hours on Saturdays, Sundays, and holidays, we will adjust the charges as necessary for customers who have detoured to Route 8. Please see Attachment-3 [PDF: 454KB] for details.

Four. Traffic regulation contents

In carrying out the construction, we will implement face-to-face traffic restrictions (up to about 5.5km) throughout the day. Since heavy traffic is expected to occur on both the upper and lower lanes, we will operate in 3 lanes (2 + 1 lanes). In order to change the number of lanes that can be passed according to the busy hours, the road zipper system will switch lane operations in a short time during the hours when traffic is relatively light, both in the early morning and in the afternoon. By changing the direction of securing two lanes according to the time of day when customers are frequently used, we will operate lanes so as to reduce inconvenience to customers.
During the switching time, it may be crowded because it will be temporarily operated in one lane on each side. Please observe the regulated speed and follow the local information signs.

Five. Request when using

  1. Face-to-face traffic will be restricted throughout the construction section for approximately 5.5km. The number of lanes has been reduced from the current two lanes on each side to one lane, and it is predicted that there will be a maximum of 10km of traffic, starting from the construction site. To do.
    • During the all-day face-to-face traffic regulation period, during some hours on Saturdays, Sundays, and holidays, we will adjust the charges as necessary for customers who have detoured to Route 8. Please see Attachment-3 [PDF: 454KB] for details.
  2. Since the driving lane and shoulders are narrow in the two-way traffic restricted section, please observe the regulated speed when driving, secure the inter-vehicle distance, and be careful about rear-end collisions. In addition, the lanes will change significantly before and after the two-way traffic regulation section, so please follow the local information signs.
  3. Vehicles for construction work may enter and leave the area around the construction site, so please be careful when traveling ahead.
  4. During the construction period, we will provide traffic congestion information using LED information boards, provide construction regulation information using road information boards and road signs, and call attention to driving safely. Please check this information before driving and drive safely.

◇ Image photo of providing information around construction regulations

Image image of road information board
Road information board
Image of LED information board
LED information board

6. Outline of floor slab replacement work

Floor slab replacement work is a work to replace a concrete slab that is damaged due to deterioration or an increase in large vehicles with a new prestressed concrete slab that has higher durability. In addition, high-performance floor slab waterproofing is also implemented on the waterproof layer to prevent deterioration of the concrete floor slab.

Image image of outline of floor slab replacement work
Floor slab replacement work (Example of "Hokuriku Expressway Takase Bridge (In-bound line)" carried out in the fall of 2018)
Image of floor slab replacement work (example of "Hokuriku Expressway Takase Bridge (In-bound line)" carried out in the fall of 2018)
Damage to Sakaehashi and Kaikugawabashi
Photo of cracks in concrete
Photograph of concrete sedimentation
Photograph of corrosion at the end of the girder

◇ Efforts to minimize inconvenience to customers due to construction work

Adoption of precast products for the purpose of shortening the construction period and improving quality

  • By adopting precast (products manufactured in advance at factories, etc.) PC floor slabs, the construction period is shortened and the regulation period is shortened as much as possible.

Expressway renewal project

Expressway renewal project logo image image 2

Now, safety and security for the next generation.
NEXCO EAST will work on the renewal and repair business of Expressway order to deliver safety and security to everyone.

More information on the Expressway renewal project

Two-dimensional code image link to the Expressway renewal project page (external link)

Search for "high-speed renewal" or visit the special website.

Image link (external link) to download page of Adobe Acrobat Reader

To view the PDF file, you need the Adobe Systems plug-in software "Acrobat Reader (Japanese version)". If you do not have​​​ Download from here (free)Please use it.