Expressway renewal project
【E8】北陸道(下り線)名立谷浜IC⇒上越JCT間
夜間通行止め及び昼夜連続車線規制のお知らせ (第2報)
- Corporate Top
- Press Room
- Press Release Niigata office
- [E8] Between Hokuriku Expressway (Out-bound line) Meitachi Tanihama IC ⇒ Joetsu JCT Notice of night traffic closure and day-night continuous lane regulation (2nd report)
We will carry out tunnel reinforcement work from April to August
March 19, 2018
East Nippon Expressway Co., Ltd.
Niigata office
NEXCO EAST Niigata branch (Niigata city Chuo Ward)E8Tunnel reinforcement work is being carried out from October, 2017 era between Mainichi Tanihama Interchange (IC) and Joetsu Junction (JCT) of the Hokuriku Expressway (down line). Thank you very much for your understanding and cooperation in construction. Because of the winter snow-ice period, we temporarily canceled the regulations associated with construction, but we will restart construction from April 17 (Tue), 2018.
This time we will inform you of regulatory schedule until the beginning of August of 2018 as a second report. During the construction period, we have prepared a website dedicated to the construction work External link: A new window will be provided, so please refer to it when using the Expressway.
We apologize for the inconvenience to our customers, but we ask for your understanding and cooperation as it is necessary for the safe and comfortable use of the Expressway.
Route | Hokuriku Expressway |
---|---|
section | Meitetsu Tanihama IC-Joetsu JCT (Out-bound line) |
Implementation period |
|
Regulation method | 1. Closed at night 2. Restricted lanes during the day and night |
Time | From 12:00 to 6:00 the next morning, 2. 24 hours all day |
Construction content | Tunnel reinforcement work |
Remarks | * Regulation period / time may be changed or canceled depending on the weather. |
Schedule for night traffic and day / night continuous lane regulation
E8 Hokuriku Expressway, we will carry out night traffic closures and day and night continuous lane restrictions according to the following schedule.
Implementation time
Closed at night: From 20:00 each day to 6:00 the next morning
Day / night continuous lane regulation: 24 hours a day
- We will inform you of the regulation implementation date after the middle of August, 2018 again at a later date.
- For closed sections and detours, Attachment 1 [PDF: 198KB] Please check.
- Regarding adjustment of transit charges due to suspension of traffic, Attachment 2 [PDF: 57KB] Please check.
- NEXCO EAST's road traffic information providing services etc.,Attachment 3 [PDF: 92KB] Please check.
- Regarding the suspension of the Joshinetsu Expressway scheduled to be close at the same time as this construction, Attachment 4 [PDF: 220KB] Please check.
- For all scheduled road closures on the Hokuriku and Joshinetsu roads, Attachment 5 [PDF: 220KB] Please check.
Outline of tunnel reinforcement work
Tunnel reinforcement work is a work to install an invert (a lining part that is finished in an inverted arch on the bottom of the tunnel) against the increase in earth pressure around the tunnel, increasing the proof stress of the tunnel, It has the effect of preventing deformation.
Tunnel reinforcement work (other cases)
Lane control methods
Expressway renewal project
Now, bring safety and security to the next generation.
NEXCO EAST will work on updating and repairing highways to deliver safety and security to everyone.
More information on the Expressway renewal project
Search with "fast renewal" or Special website Please check. For this construction, we are planning a site tour for the media. We will let you know when the date is decided.
2018/03/19 18: 00 Attachment 5 correction
2018/03/29 14: 00 Attachment 4 correction