[E18] Joshin-Etsu Expressway between Sakaki IC and Koshoku JCT (upper and lower lines)
Notice of day and night continuous face-to-face traffic regulation due to landslide countermeasure construction
- Corporate Top
- Press Room
- Press Release Kanto Regional Head Office
- [E18] Joshin-Etsu Expressway between Sakaki IC and Koshoku JCT (upper and lower lines) Notification of day and night continuous face-to-face traffic regulation due to landslide countermeasure construction
In the E18 Joshinetsu Expressway between Sakaki IC and Koshoku JCT where two-way traffic is restricted, there is a traffic jam of about 5 km on the In-bound line mainly during the morning commuting hours, and traffic congestion is occurring inside the tunnel.
In addition, there is a traffic jam of about 3 km on Out-bound line, mainly in the evening.
When driving in a restricted section, please comply with the speed limit, keep the lane distance, and be careful not to have a rear-end collision.
The latest regulatory information isDraTraPlease see.
February 2, 2023
East Nippon Expressway Co., Ltd.
Nagano construction office
NEXCO EAST At the Nagano Construction Office (Nagano City, Nagano Prefecture), E18 Joshin-Etsu Expressway (hereinafter referred to as "Joshinetsu Expressway") Upper and lower lines Between Sakaki Interchange (hereinafter referred to as "IC") and Sarahani Junction (hereinafter referred to as "JCT"), we will implement continuous face-to-face traffic restrictions day and night to carry out landslide countermeasure work. We apologize for any inconvenience this may cause, but we ask that you comply with the speed limit within the restricted area and cooperate in driving safely.
In addition, traffic congestion is expected due to face-to-face traffic restrictions. When you go out, please check the traffic information on websites such as "DraTra". This construction is necessary for you to use the Expressway safely and comfortably, so we ask for your understanding and cooperation.
1. Overview of face-to-face traffic regulation
Route | E18 Joshin-Etsu Expressway |
---|---|
section | Sakaki IC - Koshoku JCT Up and down lines |
Implementation period | Day and night continuous face-to-face traffic regulation: February 28 (Tuesday) to April 25 (Tuesday), 2023 |
Time zone | 24 hours (all day) |
Construction content | Landslide countermeasure construction (Please see "5. Construction Overview") |
- From April 26th (Wednesday) to April 27th (Thursday), the lane will be restricted day and night.
- Face-to-face traffic regulation will be implemented day and night on Saturdays and Sundays.
- The regulation period may change depending on the weather and work progress.
2. Construction section
Joshinetsu Expressway Sakaki IC - Koshoku JCT (upper and lower lines)
3. Congestion prediction
- Due to two-way traffic restrictions, traffic congestion is expected on both the up and down lines on the following dates.
Even on non-colored days, depending on traffic conditions, traffic jams of less than 3km may occur.
Usage Guide
[In-In-bound line (for Joetsu ⇒ for Takasaki)]
On the In-bound line, traffic jams of up to approximately 6 km (approximately 20 minutes of transit time) are predicted beginning in the construction restricted section on weekday mornings and weekend evenings.
【Usage Guide】
- weekday
- holiday
[Out-bound (Takasaki direction ⇒ Joetsu direction)]
On the Out-bound line, congestion of up to 6 km (approximately 20 minutes of transit time) is predicted starting from the construction restricted section in the evenings of weekdays and holidays.
- weekday
- holiday
We apologize for the inconvenience, but please check the latest traffic conditions when you go out, and please cooperate with safe driving.
Four. Requests when driving in two-way restricted sections
Due to the construction work, two-way traffic will be restricted for about 2.0 km on the inbound and outbound lines, so the current four lanes of inbound and outbound lines will be reduced to two lanes. Since the lane width is narrow in the two-way traffic regulation section, please observe the speed limit when driving, secure the distance between vehicles, and be careful of rear-end collisions.
- Due to two-way traffic restrictions, lanes will be reduced in the front and back, so please drive according to the construction notice signs. In addition, it is necessary to change lanes or merge at times 1 to 4 shown in the figure below.
- Construction vehicles may come and go around the construction site, so please be careful when driving ahead.
- Before going out, please check the latest lane regulations and traffic information on the website described in "6. How to obtain traffic information". Also, when using it, please leave with plenty of time to spare.
- During the construction period, we will provide construction regulation information using road signs and call attention to ensure safe driving. Please check these information before driving and drive safely.
Five. Construction outline
E18 Joshinetsu Expressway Between Sakaki IC and Sarahani JCT, we will construct a main line protection facility as a slope landslide countermeasure work. Currently, the construction is at its peak, and face-to-face traffic will be restricted and installed at night. As for the Out-bound line side, the installation was completed by day and night continuous face-to-face traffic restrictions from October 12 ~ December 19, Reiwa 4, and the remaining In-bound line side will be installed under this regulation.
We apologize for any inconvenience this may cause, but this is necessary for the safe and comfortable use of the Expressway, so we ask for your understanding and cooperation.
6. How to obtain traffic information
(1) Guidance by distribution / posting
- Information on posters, leaflets and digital signage will be posted at nearby tollhouses, SA / PA.
- A banner will be posted on the overpass on the Expressway.
(2) Road traffic information that can be obtained before going out
- NEXCO EAST Expressway Traffic Information Site "DraTra"
Real-time information[Mobile] http://m.drivetraffic.jp/Lane regulation information - NEXCO東日本お客さまセンター
ナビダイヤル 0570-024-024(24時間オペレーターが対応)
または 03-5308-2424 - 日本道路交通情報センター(JARTIC)の道路交通情報
全国共通ダイヤル 050-3369-6666
(携帯短縮ダイヤル #8011)
※全国どこからでも最寄りの情報センターに接続します。
全国・関東甲信越情報 050-3369-6600
長野情報 050-3369-6620
【PC】https://www.jartic.or.jp/
(3) Road traffic information available while using the Expressway
- You can check the latest information on traffic jams and travel time on the official LINE account.
- Road information board
- Highway radio (AM1620kHz)
The highway radio section is indicated by signs on the Expressway. - Highway Information Terminal
Wide-area road information is provided in an easy-to-understand manner on the monitor screens installed in SA / PA.
- Information is also distributed on the official Twitter account.
"NEXCO EAST (Kanto)" (@e_nexco_kanto) Real-time traffic information
To view the PDF file, you need the Adobe Systems plug-in software "Acrobat Reader (Japanese version)". If you do not have Download from here (free)Please use it.