Stopping excavation in tunnel construction on the main road of the outer ring road in Tokyo
About the cause and the situation of repair
- Corporate Top
- Press Room
- Press Release Kanto Regional Head Office
- About the cause of the suspension of excavation in the tunnel construction of the main road of the outer ring road in Tokyo and the situation of repair
Thursday, April 28, 4th year of Reiwa
East Nippon Expressway Company Limited Kanto Regional Head Office
Kanto Regional Development Bureau, Ministry of Land, Infrastructure, Transport and Tourism
On April 12, regarding the shield machine of the main line tunnel (southbound) started from Oizumi JCT (Oizumi-machi, Nerima-ku), we announced "Stop excavation in the construction of the main line tunnel on the outer ring road in Tokyo". is.
We will announce the causes and repair status that have been clarified so far as shown in the attached sheet [PDF: 171KB].
We apologize to the local people and other people for the suspension of construction work.