[E18] Joshin-Etsu Expressway Out-bound Line Matsuida-Myogi IC ⇒ Usui-Karuizawa IC
Notice of day and night continuous lane regulation due to tunnel renewal work
[2nd report]
Expressway with peace of mind for a long period of time-
- Corporate Top
- Press Room
- Press Release Kanto Regional Head Office
- [E18] Joshin-Etsu Expressway Out-bound Line Matsuida-Myogi IC ⇒ Usui-Karuizawa IC Notice of day and night continuous lane regulation due to tunnel renewal work [2nd report]
The latest regulatory information isDraTraPlease see.
February 14, 4th year of Reiwa
East Nippon Expressway Co., Ltd.
Nagano Construction Office
At NEXCO EAST Nagano Construction Office (Nagano City, Nagano Prefecture), from the E18 Joshin-Etsu Expressway (hereinafter "Joshin-etsu Expressway") Out-bound line Matsuida-Myogi interchange (hereinafter "IC") Usui-Karuizawa (light) Karuizawa) In order to reinforce the tunnel in some sections of the IC, lane restrictions will be enforced continuously during the day and night on weekdays.
We apologize for the inconvenience caused to our customers, but we ask for your understanding and cooperation so that you will have time to spare when you go out.
1. 1. Restricted section and date and time
- Joshinetsu Expressway Out-bound Line Matsuida-Myogi IC ⇒ Usui-Karuizawa IC
- Date and time
February 28, 4th year of Reiwa-Friday, April 22nd, 4th year of Reiwa- Regulations will be enforced day and night, starting at 6 o'clock on Monday ⇒ will be lifted at 8 o'clock on Friday.
- The following traffic congestion periods are not regulated.
- We will inform you of the implementation dates after May, 4th year of Reiwa.
- In the construction section, it is predicted that it will take longer than usual to pass due to the influence of the regulated speed, so please go out with plenty of time.
- The regulation period may change depending on the progress of construction work.
- The dates for implementation until April 4th of Reiwa are as shown in the calendar below.
【Usage Guide】
: Day and night continuous lane regulation implementation date
* We will inform you of future regulation schedules.
2. Construction overview
At the Takaiwayama tunnel between the Joshinetsu Expressway down line Matsuida-Myogi IC and Usui-Karuizawa IC, the road surface is uplifted or damaged due to damage to the lower part of the tunnel, so tunnel reinforcement work will be carried out.
Specifically, after excavating the road surface, concrete (invert) will be installed to reinforce the bottom of the tunnel, and then pavement work will be carried out to return it to a road that can be driven. (Please refer to each figure below)
From March to April of Reiwa 4, the passages in the tunnel (watcher passage, audit passage) will be removed as a preliminary step to the installation of the invert.
Since these works take a long time, we will carry out the work while continuously implementing lane restrictions during the day and night.
In addition, we will strengthen the tunnel structure and repair damage to the paved road surface to improve safety. In addition, lane restrictions will not be enforced on weekends and holidays so as not to cause inconvenience to customers as much as possible.
We ask for your understanding and cooperation as this work is necessary to use the expressway safely and comfortably.
[Request when using during construction]
- If you use this section, please leave plenty of time.
- There are construction vehicles coming and going around the construction site, so please be careful ahead.
- Since the driving lane and shoulders are narrow in the regulated section, please observe the regulated speed when driving, secure the distance between vehicles, and be careful about rear-end collisions.
In addition, lanes will change before and after the restricted section, so please follow the signboards. - During the construction period, please check the latest regulatory information and traffic information on road information boards, SA / PA digital signage, and DraTra
■ Regulatory status
The maximum speed is 50km / h in the lane-restricted section. When using, please follow the local signs and drive safely.
■ Main construction contents (installation of invert)
Inverts are installed to improve stability in order to make the ring-shaped stronger structure for tunnels where excessive force is applied from around the tunnel.
- Invert is to integrate the bottom of the tunnel into the reverse arch with concrete, which increases the yield strength and prevents subsidence and deformation.
■ Work image
As shown in the picture below, ①⇒②⇒③⇒④ is partially repeated.
[Removal of guard passage / audit road]
3. How to obtain traffic information
(1) Guidance by distribution / posting
- Information by digital signage will be posted on the surrounding SA / PA.
- A banner will be posted on the overpass on the Expressway.
(2) Road traffic information that can be obtained before going out
- NEXCO東日本お客さまセンター(24時間オペレーターが対応)
ナビダイヤル:0570-024-024
またはTEL:03-5308-2424 - NEXCO EAST Expressway Traffic Information Site "DraTra"Real-time information[Mobile] http://m.drivetraffic.jp/Construction regulation information
- 日本道路交通情報センター(JARTIC) 道路交通情報
全国共通ダイヤル 050-3369-6666(携帯短縮ダイヤル #8011)
※全国どこからでも最寄りの情報センターに接続します。
全国・関東甲信越情報 050-3369-6600
群馬情報 050-3369-6610
長野情報 050-3369-6620
【PC】https://www.jartic.or.jp/
(3) Road traffic information available while using the Expressway
- Road information board
- Highway radio (AM1620kHz)
The highway radio section is indicated by signs on the Expressway. - Highway Information Terminal
We will inform you of road information in an easy-to-understand manner by the monitor screens installed in SA / PA. - VICS
You can get road traffic information with VICS-compatible car navigation and other on-board devices.
- Information is also distributed on the official Twitter account.
"NEXCO EAST (Kanto)" (@e_nexco_kanto) Real-time traffic information
Four. Reference material
Day and night continuous lane regulation <Position map> [PDF: 168KB]
Expressway renewal project
Now, safety and security are passed on to the next generation.
NEXCO EAST will work on the renewal and repair business of Expressway order to deliver safety and security to everyone.
The NEXCO EAST Group has positioned the period from 2021 to 2025 as "a period that contributes to the achievement of the SDGs and transforms into a new future society," and is making various efforts.
We believe that this "tunnel renewal work" will contribute to the SDGs targets 8, 9, and 11 as business activities that will lead to the development of safe, secure, and reliable infrastructure.