Tohoku Expressway (In-bound line) Tochigi IC-Iwafune JCT Day and night
One-lane regulation notice
From Monday, October 20 to Friday, October 24
-During the construction period, traffic congestion of about 10km is expected in the evening-
- Corporate Top
- Press Room
- Press Release Kanto Regional Head Office
- Tohoku Expressway (In-bound line) Tochigi IC-Iwafune JCT Notice of single lane regulation day and night
October 6, 2014
*Added on October 23, 2014
East Nippon Expressway Co., Ltd.
Utsunomiya Management Office
(Added on October 23, 2014)
Bridge repair work between Tohoku Expressway (In-bound line) Tochigi Interchange (IC) and Iwafune JCT, which was carried out under the single-lane regulation for continuous day and night from October 20th (Monday) to 24th (Friday) Progressed smoothly than planned, Ends at 14:30 on Thursday, 23rd I will let you know. Thank you for your cooperation during the construction period.
NEXCO EAST Utsunomiya Management Office (Kanuma City, Tochigi Prefecture) will expand the bridge between the Tochigi Interchange (IC) and Iwafune JCT (In-bound line) due to the installation of the uphill lane near Iwafune Junction (JCT) on the Tohoku Expressway. .. For this reason, we will implement traffic regulations that reduce the number of lanes in a row day and night.
During the construction period, traffic is expected to be around 10km during the high traffic hours in the evening, so please allow plenty of time when you go out. We apologize for the inconvenience, and we appreciate your understanding and cooperation.
1 Restricted section
Tohoku Expressway (In-bound line) Between Tochigi IC and Iwafune JCT
Day and night continuous lane regulation (regulation extension of about 2 km)
2 date and time
Monday, October 20, 2014, 8am-It ended at 14:30 on Thursday, October 23.
- If stormy weather is expected during the week of October 20 and construction cannot be completed, postponement will be postponed to the week of October 27 (no Saturday or Sunday restrictions will be applied).
- In case of stormy weather, the decision will be made by 18:00 the day before (October 19th).
- For the latest information, please see [Attachment (2) Road traffic information available before going out] such as NEXCO EAST Road Information Site "DraTra". (Attachment [PDF: 56KB] reference)
3 Construction overview
Tohoku Expressway Iwafune JCT ~ Tochigi between the IC (Out-bound the line), in traffic congestion period such as Bon and tourist season, In-bound traffic intensive congestion rate reduction due to slope causes has occurred. As part of this traffic congestion countermeasure, we are constructing a new uphill lane. Construction started in January 2014 and is expected to take approximately two years by the end of FY27.
(1) Installation of climbing lane
Tohoku Expressway (Out-bound line) 62.6KP-67.6KP (approx. 5.0km) Iwafune JCT A new uphill lane will be established at the junction lane, but if there is no space to widen on the Out-bound line side, the In-bound line will be outside first. After widening, move the Out-bound line to set up the lane.
(2) Construction content
This work is a work to replace the existing In-bound line bridge with a new one in connection with the existing bridge joint (expansion device) when expanding the bridge. In this construction, it is necessary to control the lanes continuously in the day and night in order to replace all existing bridge joints (expansion devices) and then replace them.
To view the PDF file, you need the Adobe Systems plug-in software "Acrobat Reader (Japanese version)". If you do not have Download from here (free)Please use it.