NEXCO EAST Hokkaido Regional Head Office (Sapporo-shi Atsubetsu-ku) is responsible for emergency work for road level difference near N87.0KP (Ebe Otomachi, Takigawa City) between Doki Do-O Expressway Takigawa Interchange (IC) and Fukagawa Junction (JCT) (Asahikawa direction). I will inform you that it was completed today at 14:00.
In addition, emergency work was carried out today by removing the road closures at 7 am when it was confirmed that driving in the overtaking lane was safe, and by restricting lanes.
We deeply apologize for any inconvenience caused by the long-term emergency construction.
1 Road closure status
Road name | direction | section | Start date and time | Release date and time |
---|---|---|---|---|
Do-O Expressway | Asahikawa direction | Takigawa IC ⇒ Fukagawa JCT | 12/11 9:00 | 12/12 7:00 |
2 Damage situation
There are 2 steps with a length of about 10 m and 2 points with a length of about 2 m on the main road from the shoulder to the driving lane, and the maximum step is about 15 cm.