About major renewal work schedule in 2020
~ Expressway Renewal Project ~
- Corporate Top
- Notice
- Business announcements
- About major renewal work schedule in 2020
April 15, 2nd year
East Japan Expressway Co., Ltd.
NEXCO EAST (Chiyoda-ku, Tokyo) has been implementing a Expressway renewal project (large-scale renewal and large-scale repair business) since FY2015 to ensure the long-term health of the Expressway network. As shown in the table below, we plan to replace bridge deck slabs with 10 bridges in FY2020. We require long-term traffic regulation at the construction site, and we apologize for any inconvenience this may cause to customers using the Expressway and the people along the road. We appreciate your understanding and cooperation.
1 List of bridge deck replacement works with long-term traffic restrictions
number | Construction name | Bridge name | Position (between ICs) | Traffic regulation | Scheduled construction time |
---|---|---|---|---|---|
【1】 | Yubari River Bridge (Out-bound line) | May-July 2020 | |||
【2】 | Tohoku Expressway Towada Jurisdiction Expressway Renewal work | Kosakagawa Bridge (In-bound line) | Towada IC-Kosaka IC | ||
【3】 | Kosaka IC-Ikarugaseki IC | ||||
【4】 | Tohoku Expressway Takigawa Bridge floor slab replacement work | Takina River Bridge (Out-bound line) Kuzumaru River Bridge (Out-bound line) | Hanamaki IC-Morioka Minami IC | August-November 2020 | |
【5】 | Tohoku Expressway Miyagi Shiraishigawa Bridge floor plate replacement work | Miyagi Shiraishigawa Bridge (upper and lower lines) | Kunimi IC-Shiraishi IC | May-July 2020 September to November 2020 | |
【6】 | Yabuki IC-Sukagawa IC | September to November 2020 | |||
【7】 | Nagano Expressway Kikuzo Bridge floor plate replacement work | Kikuzo Bridge (In-bound line) | Azumino IC-Mamisho IC | May-July 2020 | |
【8】 | Kan-Etsu Expressway Matsukawa Bridge floor slab replacement work | Matsukawa Bridge (In-bound line) | Mizukami IC to Yuzawa IC | May-July 2020 September to November 2020 |
2 List of other renewal works with long-term traffic regulations
number | Construction name | Tunnel name etc. | Position (between ICs) | Traffic regulation | Scheduled construction time |
---|---|---|---|---|---|
【9】 | Lane regulation | April to December 2020 | |||
Joshin-Etsu Expressway Horai Construction | (Upper and lower lines) | Day and night Lane regulation |
3 Major construction sites and scheduled time for FY2020
<Countermeasure example>
4 Other renewal work planned for 2020
NEXCO EAST will continue to install high-performance waterproofing work to improve the durability of bridge decks and work to secure long-term stability of the slope.
Bridge repair | Cut slope repair | Embankment slope repair | Repair of drainage facility | |
High performance floor waterproofing | Ground anchor | Hard rock ground removal | Measures to eliminate seepage water | Jumping measures, etc. |
About 65 bridges | About 5 places | One place | About 40 places | About 210 places |
Now, bring safety and security to the next generation.
NEXCO EAST will work on updating and repairing highways to deliver safety and security to everyone.