Regarding the permanent implementation of the special measures for advance payments (Large of use)

令和7年4月18日
東日本高速道路株式会社

NEXCO EAST will make the special measures (Large use) for advance payments for construction projects permanent from fiscal year 2025 onwards.

Eligible down payments

An advance payment for a new construction contract.

Details of Large use

The special provision that Large the uses of advance payments to include site management expenses, general administrative expenses, etc. required for the construction of the work in question will be made permanent.

(Note 1)
The maximum amount of the prepayment to be allocated to these is 25/100 of the prepayment amount.
(Note 2)
This special measure can also be applied to works for which a contract has already been concluded.
In that case, you need to change the contract contract, so please consult the contract department in charge of the contract.